PLANNING COMMISSION AGENDA
Tuesday February 26, 2008, 7:00 pm
Agenda Item Description Meeting
Dates**
Staff
Recommendation
PC
Recommendation
I. Invocation
II. Call to Order
III. Pledge of
Allegiance
IV. Public Comment
V. Approval of
Minutes
Minutes from the January 29,
2008 Planning Commission
Meeting
Approval
VI. Use Permits
U08-001
VC08-001
Land Road
Celestino Martinez
To obtain a use permit to
develop a landscape
business. The applicant is
also requesting the following
concurrent variance:
To allow access from a local
road (Article 19.4.27 Section
B.1)
CZIM –
1/23/08
DRB- 2/5/08
PC- 2/26/08
Denial
Denial
U07-011/
VC07-017
13620 Hopewell
Road
Monticello Real
Estate Invest, LLC
JT Adams
Use Permit for a Private
School to be developed
with 5 buildings for a total of
63,400 square feet with a
maximum of 325 students for
Kindergarten – 8th graders.
The applicant is also
requesting the following 5-
part concurrent variance:
1) To reduce the building
setback along the north
property line from 100 feet
to 85 feet (19.4.40.B.3)
2) To reduce the 75-foot
buffer and 10-foot
improvement setback to the
extent necessary to all the
septic field to encroach.
(Article 12H.3.1C.2.)
3) To increase the 20 foot
setback from the landscape
strip to 500 feet.
(12H.3.5.C.1)
4) To allow parking between
the right of way and the
building. (Article 12H.3.5.F.3)
5) To reduce parking from
171 spaces to 70 spaces
(Article 18.2.1)
CZIM – 1/2/08
DRB- 1/8/08
PC- 1/29/08
PC-2/26/08
Withdrawal
Withdrawal
XI. ADJOURN
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
2
PETITION NUMBER(S):
U08-001/VC08-001
PROJECT NAME
PROPERTY INFORMATION
ADDRESS Land Road (gravel road)
DISTRICT, LAND LOT 2/2 255
OVERLAY DISTRICT Northwest Fulton Overlay
EXISTING ZONING AG-1 (Agricultural)
ACRES 10.04
EXISTING USE Undeveloped
PROPOSED USE Use Permit for a Landscape Business (Article 19.4.27)
OWNER Celestino Martinez
ADDRESS 16164 Hopewell Rd.
PETITIONER/REPRESENTATIVE Celestino Martinez
ADDRESS 16164 Hopewell Rd.
Milton, GA 30004
PHONE 678-618-8375
INTENT
To obtain a use permit to develop a landscape business. The applicant is also requesting a
concurrent variance:
1) To allow access from a local road. (Article 19.4.27 Section B.1)
COMMUNITY DEVELOPMENT DEPARTMENT RECOMMENDATION
U08-001 – DENIAL
VC08-001 - DENIAL
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
3
LOCATION MAP
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
4
CURRENT ZONING MAP
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
5
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeti
PC-P
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
6
ng Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
lanning Commission; MCC-Mayor and City Council
SITE PLAN – January 10, 2008
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
7
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
8
SOUTHWEST VIEW OF SUBJECT SITE FROM LAND ROAD
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
9
PROPERTIES TO THE NORTH OF SUBJECT SITE
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
10
SOUTH VIEW OF SUBJECT SITE FROM LAND ROAD
SUBJECT SITE:
The subject site is a 10.04 acre tract of agriculturally zoned land, located on the southern and
western side of Land Road. The subject site is currently undeveloped, but is used as a staging
ground for a landscape business. It is located within the Agricultural, Forestry and Mining Land
Use designation on the Focus Fulton 2025 Comprehensive Land Use Plan.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
11
Existing uses and zoning of nearby property (See Map following table)
Location Parcel / Zoning
Petition Zoning / Name
Approved
Density/Min.
Heated Floor Area
North/Northwest 1
(AG-1)
AG-1 Agricultural
Scattered homes Min. 1 unit/acre
Northeast 2
(AG-1)
AG-1 Agricultural
Undeveloped Min. 1 unit/acre
East 3
(AG-1)
AG-1 Agricultural
Korean Christian Prayer
Ministries
Min. 1 unit/acre
South/West 4
(AG-1)
AG-1 Agricultural
Scattered homes Min. 1 unit/acre
Further South 5
(AG-1)
AG-1 Agricultural
Scattered homes Min. 1 unit/acre
Southwest 6
(AG-1)
AG-1 Agricultural
Undeveloped Min. 1 unit/acre
Further
Southwest/West
7
(AG-1)
AG-1 Agricultural
Scattered homes Min. 1 unit/acre
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
12
EXISTING USES AND ZONING MAP
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
13
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
14
In the interest of the public health, safety and welfare, the Mayor and City Council may
exercise limited discretion in evaluating the site proposed for a use that requires a Use Permit. In
exercising such discretion pertaining to the subject use, the Mayor and City Council shall
consider each of the following as outlined in Article 19.2.4 of the Zoning Ordinance; Use Permit
Considerations. Staff has reviewed said items pertaining to the subject use, and, offers the
following comments:
A. Whether the proposed use is consistent with the land use or economic development
plans adopted by the Mayor and City Council:
Provided the applicant complies with the Recommended Conditions of this petition and
the Use Permit requirements of Article 19.4.27. of the Zoning Ordinance, the proposed
development may be consistent with the intent and following policies of the
Comprehensive Plan:
• Encourage development consistent with the surrounding scale, transition of
densities and uses, and Comprehensive Plan policies, where appropriate.
B. Compatibility with land uses and zoning districts in the vicinity of the property for which
the use permit is proposed;
If developed in accordance with Staff’s Recommended Conditions and the provisions of
the Zoning Ordinance, the proposed landscape business may be compatible with other
land uses in the surrounding area.
C. Whether the proposed use may violate local, state and/or federal statutes, ordinances or
regulations governing land development;
The proposed use does not violate any known local, state and/or federal statutes,
ordinances or regulations governing land development.
D. The effect of the proposed use on traffic flow, vehicular and pedestrian, along adjoining
streets;
It is Staff’s opinion that the proposed use will generate a minimal increase in traffic.
However, the location of the subject site on a local street is inconsistent with
development standards per Article 19.4.27. There are deliveries made by 18 wheel semi-
trucks to the site that have a negative impact on the area and the gravel road. Staff is
of the opinion that this proposed use would have a negative impact on surrounding
residentially developed properties.
E. The location and number of off-street parking spaces;
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
15
Article 18.2.1 requires the applicant to provide a minimum of 3 parking spaces per 1,000
sq. ft. of general office space. Article 19.4.27 requires the applicant to locate parking
outside of the minimum 60-foot front yard building setback. The applicant’s site plan
indicates 4 parking spaces which does not meet the requirements set by Article 18.2.1.
However, it appears the applicant can meet the minimum requirements of Article 18.2.1.
F. The amount and location of open space;
The applicant’s site plan indicates that the subject site is undeveloped. Staff is of the
opinion that the proposed development may provide adequate open space for the
proposed development.
G. Protective screening;
If developed in accordance with the requirements of the Zoning Ordinance and the
Northwest Fulton Overlay District, the buffer and landscape strip requirements and the
existing screening around the structures will provide adequate screening for the
proposed development. To help further screen the landscape materials from adjacent
properties to the north, Staff recommends an 8’ high opaque fence along the frontage
of Land Road where residential structures are located across the street.
H. Hours and manner of operation;
The applicant states that the hours of operation will be from 7:00am to 7:00pm, Monday
through Friday, which conforms to the hours of operation standards in Article 19.4.27.
Staff notes that delivery of materials occurs before 7:00am.
I. Outdoor lighting;
At the time of Land Disturbance Permit the site shall be in compliance with Article 12H.3.4
of the Northwest Fulton Overlay District regarding outdoor lighting. Staff notes that the
subject site’s required buffers, and existing screening, will help mitigate the impact of any
possible lights on the adjacent properties.
J. Ingress and egress to the property.
The applicant’s site plan indicates one curb cut. The proposed curb cut is located east
of the existing curb cut that is being currently utilized. Staff notes that the applicant is
proposing a gravel drive.
Staff notes that access from the subject site to a local road is not permitted within the
development standards of Article 19.4.27. Furthermore, Staff is of the opinion that access
to the subject site from a local road would cause unnecessary detriment to nearby
property owners, and that delivery truck traffic would not be conducive to a residential
environment. Therefore, Staff recommends DENIAL of VC08-001. Lastly, Staff notes that
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
16
there is no possible solution to mitigate access from a local road to the subject site due
to its location and recommends DENIAL of U08-001.
SITE PLAN ANALYSIS
Based on the applicant’s site plan submitted to the Community Development Department on
January 10, 2008, Staff offers the following considerations:
Northwest Overlay District
BUILDING HEIGHT
Article 12H.3.5 Section D.1 of the Northwest Overlay District requires a maximum height limit of
two stories with the maximum height 30 feet from average-finished grade to the bottom of the
roof eave. The applicant has not specifically indicated the height of the proposed structure,
but must meet this standard before obtaining a building permit. If approved, the applicant’s
proposed building would require a review by the City of Milton Design Review Board prior to the
issuance of a building permit.
LANDSCAPE STRIPS AND BUFFERS
Article 12H.3.1 Section A.1 states that all properties shall provide a minimum 10 foot-wide
landscape strip along all public streets, and it appears that the applicant has met this
requirement. Furthermore, Article 12H.3.1 Section C.2 of the Northwest Overlay District requires
a seventy-five (75) foot-wide undisturbed buffer, with a 10’ improvement setback, which shall
be located adjacent to all AG-1 zoning districts and all property zoned, used, or developed for
residential uses. In Staff’s opinion, it appears that the applicant has met this requirement.
BUILDING SETBACKS
Article 12H.3.5 Section C.2 of the Northwest Overlay District requires a maximum 30-foot building
setback from the edge of the required landscape strip and/or easements for all properties and
lots located adjacent to public rights-of-way and from 0 to 400 feet from an intersection. The
applicant’s fails to meet this requirement based on the submitted site plan, but it appears that
the applicant can meet this standard.
PARKING REQUIREMENTS
The following chart illustrates the parking required by Article 18 of the City of Milton Zoning
Ordinance for the proposed use:
Proposed Use Minimum Requirement Spaces Provided
• General Office • 3 spaces per 1,000 sq. ft. of • 4 paved spaces
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
17
(1,600 sq. ft.)
Total 1,600 sq. ft.
building area. (6 spaces)
6 spaces required
4 spaces provided
Staff notes that the applicant is providing four (4) parking spaces, which does not meet the
required six (6) parking spaces required per Article 18 of the City of Milton Zoning Ordinance. It
appears that the applicant can meet parking requirements. Staff notes that the site plan is in
compliance with the landscape and layout requirements of Article 12H.3.1 Section B.
OTHER CONSIDERATIONS
Staff is of the opinion that further buffering from adjacent property owners is necessary.
Therefore, the applicant should construct an 8’ opaque fence on the north and east property
lines to shield the use from nearby property owners.
CITY ARBORIST
An area was cleared of trees to make way for a drive, storage and parking. Reviewing the
existing vegetation and aerial photos, it appears much of the removal consisted of pine trees.
However, it cannot be determined if there were any specimen trees removed during the
process. Trees removed were chipped on site. Not an excessive amount of wood chips was
noticed, which could possibly indicate few or small trees were removed. Site does exceed the
required density units.
PUBLIC INVOLVEMENT
On January 23, 2008 the applicant was present at the Community Zoning Information Meeting
held at the Milton City Hall. There were two individuals from the community who were in
attendance at the meeting. The applicants will be presenting their plan to the Milton Design
Review Board on February 5, 2008.
Public Comments – Staff has received phone calls and emails from nearby residents. One
property owner across the street from the subject site is discontent with the proposed
landscaping business, and states that large delivery and construction trucks currently come and
go to the subject site throughout the day and night, especially early in the morning.
Staff notes that there have been concerns by local residents that the applicant is storing
muriatic acid at the subject site. In a recent site visit, Staff was unable to locate any containers
containing muriatic acid.
Staff met with the adjacent property owners to discuss issues prior to the Planning Commission
Meeting on February 26, 2008.
City of Milton Design Review Board Meeting – February 5, 2008
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
18
The following recommendations were made by the DRB:
• The applicant must bring back a plan for the garage if the use is approved by City
Council.
Public Notice Requirements
The use permit petition was advertised in the Milton Herald on February 13, 2008 and the sign
was installed before the required date of February 6, 2008 along the frontage of Land Road.
The notice of rezoning was sent, to adjacent property owners, on February 6, 2008.
CONCLUSION
Staff notes that access from the subject site to a local road is not permitted within the
development standards of Article 19.4.27. Furthermore, Staff is of the opinion that access to the
subject site from a local road would cause unnecessary detriment to nearby property owners,
and that delivery truck traffic would not be conducive to a residential environment. Therefore,
Staff recommends DENIAL of VC08-001. Lastly, Staff notes that there is no possible solution to
mitigate access from a local road to the subject site due to its location and recommends
DENIAL of U08-001.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
19
RECOMMENDED CONDITIONS
If this petition is approved by the Mayor and City Council, it should be approved USE PERMIT for
a landscape business (Article 19.4.27.) CONDITIONAL subject to the owner’s agreement to the
following enumerated conditions. Where these conditions conflict with the stipulations and
offerings contained in the Letter of Intent, these conditions shall supersede unless specifically
stipulated by the Mayor and City Council.
1) To the owner’s agreement to restrict the use of the subject property as follows:
a) Landscaping business and accessory uses at a total of 1,600 square feet of office
space.
2) To the owner’s agreement to abide by the following:
a) To the site plan received by the Milton Community Development Department on
January 10, 2008. Said site plan is conceptual only and must meet or exceed the
requirements of the Zoning Ordinance and these conditions prior to the approval
of a Land Disturbance Permit. Unless otherwise noted herein, compliance with all
conditions shall be in place prior to the issuance of the first Certificate of
Occupancy.
3) To the owner’s agreement to the following site development considerations:
a) Provide a truck routing plan and turning template for largest vehicle type that will
be accessing the site and show turnaround of vehicle on site only using one
driveway
4) To the owner’s agreement to abide by the following requirements, dedication and
improvements:
a) Driveway shall meet City of Milton Commercial Driveway Standards; driveway
design shall be approved by the Director of Public Works
i. Driveway shall intersect perpendicular to Land Road and extend 100’ at
this ninety degree angle
b) One driveway access shall be allowed within 40’ to the East of the West property
line of Tract 1
c) Commercial/heavy vehicle access to the site shall only be from Hopewell Road
d) Sight distance shall be provided according to City of Milton Standards; any
improvements to meet this requirement shall be complete before land
disturbance permit
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
20
5) To the owner’s agreement to abide by the following:
a) Provide and size a culvert at proposed driveway location; driveway apron shall be
concrete and design shall be approved by the Director of Public Works.
b) The developer’s Professional Engineer shall demonstrate to the City by
engineering analysis submitted with the LDP application, that the discharge rate
and velocity of the storm water runoff resulting from the development is restricted
to seventy-five percent (75%) of the pre-development conditions. Locations shall
be as approved by the Stormwater Engineer.
c) The water quality and detention facilities shall utilize earthen embankments, where
possible. Walled structures are not encouraged. If walled structures are proposed,
they must meet the acceptable design standards of the Department of
Community Development.
i. Detention facility shall have a six foot high, five-board equestrian style
fence with two inch by four inch welded wire constructed around it.
d) The Developer shall utilize GASWCC limited application controls. All water quality
and detention facilities shall have vegetated surfaces to be regularly maintained
by the owner.
e) Provide a maximum 75 percent impervious, per drainage basin, at maximum
build-out.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
21
APPENDIX A
Comments on Public Services and Utilities
Note: Various City and/or County departments that may or may not be affected by the proposed
development provide the following information. Comments herein are based on the applicant’s
conceptual site plan and are intended as general non-binding information and in no manner suggest a
final finding by the commenter. All projects, if approved are required to complete the City of Milton Plan
Review process prior to the commencement of any construction activity.
Fulton County Health Department:
Comments:
• Since this proposed development constitutes a premise where people work, live or congregate,
onsite sanitary facilities will be mandatory, prior to use or occupancy.
• This facility must comply with the Fulton County Clean Indoor Air Ordinance.
• The Fulton County Health Department recommends that this proposed development be
approved, provided the internal plumbing is inspected an adequate for the proposed use.
• This department is requiring that plans indicating the number and location of outside refuse
containers along with typical details of the pad and approach area for the refuse containers be
submitted for review and approval.
• Plans of this facility must be submitted to this department for review and approval.
Fulton County Tax Assessor:
Property Tax ID#: 22 -5160-0255-070-4, 22 -5160-0255-071-2
Drainage:
Flood Plain: No Flood Plain
City of Milton Fire Marshal:
Comments:
• The proposed landscape business would have a minimal impact on police.
Public Safety:
No Comment.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
22
PETITION NUMBER(S):
U07-011/VC07-017
PROJECT NAME
The Academy
PROPERTY INFORMATION
ADDRESS 13620 Hopewell Road
DISTRICT, LAND LOT 2/2 909
OVERLAY DISTRICT Northwest Fulton Overlay
EXISTING ZONING AG-1 (Agricultural)
ACRES 22.15
EXISTING USE Single Family Residence
PROPOSED USE Use Permit for a Private School for Kindergarten through 8th Grade up to
325 students (Article 19.4.40)*
OWNER Jean Elizabeth Brown Smith & James Thomas Brown
ADDRESS 13620 Hopewell Road
PETITIONER/REPRESENTATIVE Monticello Real Estate Invest, LLC / J.T. Adams
ADDRESS 8480 Holcomb Bridge Road, Suite 200
Alpharetta, GA 30022
PHONE 678-679-0365
INTENT
To develop a private school with 5 buildings for a total of 63,400 square feet with a
maximum of 325 students for Kindergarten – 8th graders. The applicant is also requesting the
following 5-part concurrent variance:
1) To reduce the building setback along the north property line from 100 feet to 85 feet
(19.4.40.B.3)
2) To reduce the 75-foot buffer and 10-foot improvement setback to the extent necessary
to allow the septic fields to encroach. (Article 12H.3.1.C.2.)
3) To increase the maximum 20 foot setback from the landscape strip to 500 feet.
(12H.3.5.C.1)
4) To allow parking between the right of way and the building. (Article 12H.3.5.F.3)
5) To reduce parking from 171 spaces to 70 spaces (Article 18.2.1)*
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
23
COMMUNITY DEVELOPMENT DEPARTMENT RECOMMENDATION
January 29, 2008
U07-011 – DEFERRAL UNTIL FEBRUARY 26, 2008
VC07-017 – DEFERRAL UNTIL FEBRUARY 26, 2008
The applicant has requested a deferral to allow more time to work with the area residents.
COMMUNITY DEVELOPMENT DEPARTMENT RECOMMENDATION
February 26, 2008
U07-011 – WITHDRAWAL
VC07-017 – WITHDRAWAL
The applicant has requested a withdrawal of this petition without prejudice.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
24
LOCATION MAP
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
25
CURRENT ZONING MAP
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
26
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeti
PC-Plan
W:\B
27
ng Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
ning Commission; MCC-Mayor and City Council
oard of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
28
SITE PLAN RECEIVED – DECEMBER 6, 2007
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
29
SUBJECT SITE LOOKING NORTH
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
30
SUBJECT SITE – LOOKING WEST
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
31
SUBJECT SITE – LOOKING EAST FROM REAR PROPERTY LINE
SUBJECT SITE:
The subject site is a 22.15 acre tract of agriculturally zoned land, located on the west side of
Hopewell Road. There is a lake on the rear of the property and a 50’ buffer and 25’ non
impervious buffer is required around it. The subject site is developed with a single-family
residence. It is located within the Agricultural, Forestry and Mining Land Use designation on the
Focus Fulton 2025 Comprehensive Land Use Plan.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
32
Existing uses and zoning of nearby property (See Map following table)
Location Parcel / Zoning
Petition Zoning / Name
Approved
Density/Min.
Heated Floor Area
Same land lot as
subject site
1
U01-13
AG-1 (Agricultural)
Chandler Academy
1,512.35 gross sq.
ft. per acre
Restricted to 60
students
East 2
(AG-1)
AG-1 (Agricultural)
Sandy Creek Farms
1 unit per acre
Est. 2,500 sq. ft.
East 3
(AG-1)
AG-1 (Agricultural)
Scattered homes
Min. 1 unit per
acre
Northeast 4
(AG-1)
AG-1 (Agricultural)
North Park Subdivision
1 unit per acre
Est. 3,000 sq. ft.
North 5
(AG-1)
AG-1 (Agricultural)
Scattered homes
Min. 1 unit per
acre
West/Northwest 6
(AG-1)
AG-1 (Agricultural)
The Lake at Cooper Sandy
1 unit per acre
Est. 3,000 sq. ft.
South 7
(AG-1)
AG-1 (Agricultural)
Scattered homes
Min. 1 unit per
acre
Further South 8
Z94-127
R-2A (Single Family Dwelling
District) Conditional
Brookshade
0.98 dwelling unit
per acre
2,500 sq. ft.
Same land lot as
subject site
9
(AG-1)
AG-1 (Agricultural)
Single-family
Min. 1 unit per
acre
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
33
EXISTING USES AND ZONING MAP
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
34
In the interest of the public health, safety and welfare, the Mayor and City Council may
exercise limited discretion in evaluating the site proposed for a use that requires a Use Permit. In
exercising such discretion pertaining to the subject use, the Mayor and City Council shall
consider each of the following as outlined in Article 19.2.4 of the Zoning Ordinance; Use Permit
Considerations. Staff has reviewed said items pertaining to the subject use, and, offers the
following comments:
K. Whether the proposed use is consistent with the land use or economic development
plans adopted by the Mayor and City Council:
Provided the applicant complies with the Recommended Conditions of this petition and
the Use Permit requirements of Article 19.4.40. of the Zoning Ordinance, the proposed
development is consistent with the intent and following policies of the Comprehensive
Plan:
• Encourage compatible institutional uses in neighborhoods and communities.
• Encourage development consistent with the surrounding scale, transition of
densities and uses, and Comprehensive Plan policies, where appropriate.
L. Compatibility with land uses and zoning districts in the vicinity of the property for which
the use permit is proposed;
If developed in accordance with Staff’s Recommended Conditions and the provisions of
the Zoning Ordinance, the proposed private school is expected to be compatible with
other land uses in the surrounding area.
M. Whether the proposed use may violate local, state and/or federal statutes, ordinances or
regulations governing land development;
The proposed use does not violate any known local, state and/or federal statutes,
ordinances or regulations governing land development.
N. The effect of the proposed use on traffic flow, vehicular and pedestrian, along adjoining
streets;
The proposed use will generate an increase in traffic but should be mitigated by the
recommended conditions.
O. The location and number of off-street parking spaces;
Article 18.2.1 requires the applicant to provide the larger of 2 per classroom or one per 35
sq. ft. in largest assembly area, whichever is larger. There will be a total of 20 classrooms
(40 spaces) and the largest assembly area is 6,000 square feet (171 spaces). Article
19.4.10 requires the applicant to locate parking outside of the minimum 60-foot front yard
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
35
building setback. In addition, the Northwest Overlay District does not allow parking to be
located to the front of a building and/or between a building and a right-of-way. The
applicant has provided approximately 70 spaces, which does not meet the required
number of spaces. The applicant is requesting concurrent variances to reduce parking
and allow parking in front of the buildings.
P. The amount and location of open space;
The applicant’s site plan indicates that approximately half of the subject site is
undeveloped. Staff is of the opinion that the proposed development will provide
adequate open space for the proposed development.
Q. Protective screening;
If developed in accordance with the requirements of the Zoning Ordinance and the
Northwest Fulton Overlay District, the buffer and landscape strip requirements will provide
adequate screening for the proposed development. Staff notes that later in the report
the requested variance to reduce the buffer is being recommended for denial.
R. Hours and manner of operation;
The applicant indicates that the hours of operation will be 7:00 am to 7:00 pm, Monday
through Friday.
S. Outdoor lighting;
At the time of Land Disturbance Permit the site shall be in compliance with Article 12H.3.4
of the Northwest Fulton Overlay District regarding outdoor lighting. Staff notes that the
subject site’s required buffers, and existing screening, will help mitigate the impact of
lights on the adjacent properties.
T. Ingress and egress to the property.
The site plan indicates the existing curb cut that provides access to the existing house. It
appears there is a drive further to the south but it does not connect with Hopewell Road.
The City of Milton Transportation Engineer has determined that the entrance of the
school should be located to north of the existing house because of the proposed
location of the Milton Trail along the west side of Hopewell Road. Staff notes that there is
an existing historic house built prior to Hopewell Road being developed, just north of the
subject site that may be negatively impacted by a decelerate lane because of its close
proximity to the street.
Staff is of the opinion that a private school is an appropriate use for this location based
on the above considerations. Therefore, Staff recommends APPROVAL CONDITIONAL of
U07-011
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
36
SITE PLAN ANALYSIS
Based on the applicant’s site plan submitted to the Community Development Department on
December 6, 2007, Staff offers the following considerations:
USE PERMIT STANDARDS
The applicant’s site plan meets all of the special use standards required for private schools,
except for Article 19.4.40 Section B.3 which states that buildings and refuse areas shall not be
located within 100 feet of a residential district and/or AG-1 district used for single family. The
applicant is requesting that the setback be reduced to 85’. It is Staff’s opinion that the private
school may be arranged in a manner to accommodate the required one-hundred (100) foot
setback from residential and AG-1 districts. The applicant has not shown evidence of a
hardship that is not self-imposed. Therefore, Staff recommends DENIAL of Part 1 of the
Concurrent Variance VC07-017.
Northwest Overlay District
BUILDING HEIGHT
Article 12H.3.5 Section D.1 of the Northwest Overlay District requires a maximum height limit of
two stories with the maximum height 30 feet from average-finished grade to the bottom of the
roof eave. The applicant’s letter of intent has indicated that they will remain within these limits.
LANDSCAPE STRIPS AND BUFFERS
Article 12H.3.1 Section A.1 of the Northwest Overlay District requires a 10-foot wide strip along
the road. It is not shown on the site plan but it appears there is sufficient area to meet this
standard.
Article 12H.3.1 Section C.1 of the Northwest Overlay District requires a seventy-five (75) foot-
wide undisturbed buffer, with a 10’ improvement setback, which shall be located adjacent to
all AG-1 zoning districts and all property zoned, used, or developed for residential uses. The
applicant has stated that the septic fields are needed in the locations indicated on the site
plan. Staff is of the opinion that the septic fields should be relocated so that the appropriate
buffer is provided to protect the adjacent residences. The applicant has not shown evidence
of a hardship that is not self-imposed. Therefore, Staff recommends DENIAL of Part 2 of the
Concurrent Variance VC07-017
BUILDING SETBACKS
Article 12H.3.5 Section C of the Northwest Overlay District requires a maximum 20-foot building
setback from the edge of the required landscape strip and/or easements for all properties and
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
37
lots located adjacent to public rights-of-way that are 0 to 400 feet from an intersection. The
applicant’s site plan does not show compliance with the requirement. It appears that the
building could be reconfigured in such a way as to meet this requirement. The applicant has
not yet shown evidence of a hardship that is not self-imposed. Therefore, Staff recommends
DENIAL of Part 3 of the Concurrent Variance VC07-017.
LOCATION OF PARKING
The applicant has requested a concurrent variance to allow parking between the street and
the building. It appears that there is sufficient room to locate the parking to the rear of the
main building if it is sited toward the right-of-way. It is Staff’s opinion that the applicant has not
shown a hardship that is not self-imposed. Therefore, Staff recommends DENIAL of Part 4 of the
Concurrent Variance VC07-017.
PARKING REQUIREMENTS
The following chart illustrates the parking required by Article 18 of the City of Milton Zoning
Ordinance for the proposed use:
Proposed Use Minimum Requirement Spaces Provided
Private school with
approximately twenty (20)
classrooms and 6,000 sq.
ft. assembly space
• Greater of 2 spaces per
classroom (40 spaces) or
one per 35 sq. ft. in largest
assembly area (171
spaces)
171 spaces required
• 70 paved spaces
70 spaces provided
Staff notes that the applicant is providing seventy (70) parking spaces, which does not meet the
required one-hundred seventy-one (171) parking spaces required per Article 18 of the City of
Milton Zoning Ordinance. Staff notes that the applicant has indicated a hardship in meeting
the required amount of parking spaces, as there are many site constraints consisting of wetland
areas, the location of the septic field, and required buffers. In addition, the parking lot will be
utilizing gravel parking to assist in the drainage of the site. Therefore, Staff recommends
APPROVAL of Part 5 of the Concurrent Variance VC07-017.
OTHER CONSIDERATIONS
The applicant has provided the following as additional building information:
Administrative Building 16,000 sq. ft.
Classroom Wings 41,000 sq. ft.
Chapel/Auditorium 6,000 sq. ft.; seating for 300 persons
Historic Structure TBD 400 sq. ft.
Number of classrooms 20
Number of students Kindergarten thru eighth grade -325
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
38
Number of staff +/- 25
CITY ARBORIST
The proposed development will not affect any specimen trees on the site and it has been
determined that there are no blue line streams that flow through the site.
PUBLIC INVOLVEMENT
On January, 2, 2008 the applicant was present at the Community Zoning Information Meeting
held at the Milton City Hall. There were forty-four people in attendance from the community.
One community member was concerned about the proposed developed, citing many
unanswered questions. The applicants presented their plan to the Milton Design Review Board
on January 8, 2008.
Public Comments – Staff has received one phone call in opposition to the proposal from the
owner of Chandler Academy that is located to the south of the subject site. Members of Staff
have also met with 3 neighborhood residents to address their concerns about the proposed
private school.
City of Milton Design Review Board Meeting – January 8, 2008
The following recommendations were made by the DRB:
• Increase buffer between septic field and adjacent property
• Comply with Northwest Overlay requirements
• No review by Board of hardships, only site plan.
Public Notice Requirements
The use permit petition was advertised in the Milton Herald on January 23, 2008 and the sign
was installed before the required date of January 2, 2008 along the frontage of Hopewell Road.
The notice of rezoning was sent, to adjacent property owners, on January 14, 2008. Because of
the applicant’s request for a 30 day deferral, the notice was re-advertised on February 13, 2008,
sign was updated on February 4, 2008, and notices resent on February 4, 2008.
Public Participation Plan and Report
The applicant has met the requirements of the Public Participation Plan. The applicant will be
required to submit the public participation report 7 days prior to the Mayor and City Council
meeting.
CONCLUSION
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
39
The proposed private school is consistent with Council and Plan Policies and compatible with
the surrounding area, if developed in accordance with the requirements of the Zoning
Ordinance and Staff’s Recommended Conditions. Based on the request of the applicant to
withdraw, Staff recommends WITHDRAWAL of U07-011/VC07-017.
RECOMMENDED CONDITIONS
If this petition is approved by the Mayor and City Council, it should be approved USE PERMIT for
a private school (Article 19.4.40) CONDITIONAL subject to the owner’s agreement to the
following enumerated conditions. Where these conditions conflict with the stipulations and
offerings contained in the Letter of Intent, these conditions shall supersede unless specifically
stipulated by the Mayor and City Council.
3) To the owner’s agreement to restrict the use of the subject property as follows:
a) Restrict the use of the subject property to a private school and accessory uses at a
maximum density of 2,862.3 square feet per acre zoned or a total of 63,400 square feet,
whichever is less.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
40
b) Restrict the number of students to 325.
4) To the owner’s agreement to abide by the following:
a) To the site plan received by the Milton Community Development Department on
December 6, 2007. Said site plan is conceptual only and must meet or exceed the
requirements of the Zoning Ordinance and these conditions prior to the approval of a
Land Disturbance Permit. Unless otherwise noted herein, compliance with all conditions
shall be in place prior to the issuance of the first Certificate of Occupancy.
5) To the owner’s agreement to the following site development considerations:
a. All building entrances shall have a direct connection to the sidewalk network.
b. The site plan must provide adequate fire truck access to all buildings on site, in alleys and
one-way conditions; as acceptable to the Transportation Engineer and Fire Marshal.
c. Provide one multi bay bicycle rack at every building.
6) To the owner’s agreement to abide by the following requirements, dedication and
improvements:
e) Prior to the approval of a Land Disturbance Permit, dedicate at no cost to the City
of Milton, sufficient land as necessary to provide the Right of Way for the
approved final site plan including the following:
i. Provide the following improvements and necessary striping as approved by
the Transportation Engineer for Milton:
1. All lanes in road improvement area shall be twelve feet wide.
2. SB Right turn lane on Hopewell Road at site driveway.
3. NB Left turn lane on Hopewell Road at site driveway.
4. Provide overlay and striping for full width of Hopewell Road the
length of property lines plus any additional taper lengths necessary.
ii. Provide at least 16 feet of right-of-way from the edge of pavement of all
abutting road improvements, along the entire property frontage, as well as
allow the necessary construction easements while the rights-of-way are
being improved.
iii. Provide a multi-use trail along the entire Hopewell Road frontage of the
entire road improvements.
1. Trail along property to be ten feet wide and located at the back of
the Right of Way.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
41
2. Trail along road improvements to be ten feet wide and located four
feet from the back of curb. Trail shall be no less than eight feet wide
and two feet from the back of curb where feasible, as approved by
the Director of Public Works.
iv. Provide a black four-board equestrian style fence adjacent to the trail as
approved by the Director of Community Development.
v. Provide six foot wide concrete sidewalk connecting the multi-use trail on
Hopewell Road to the buildings on the site with a minimum five foot grass
strip between the sidewalk and the back of curb/edge of pavement.
f) Any new required entrances shall meet the Community Service Policies and
AASHTO guidelines, or roads be reconstructed to meet such criteria, at the
approval of the Transportation Engineer for Milton.
i. Driveway access to the site shall be allowed approximately eighty-five feet
north of existing 13620 Hopewell Road driveway and at a minimum
distance to provide the necessary turn lane lengths required by the city of
Milton for the existing right turn lane into Chandler Academy for such time
this improvement may be required. There shall be no other access
driveways allowed for this site.
ii. The Hopewell Road access driveway to the school shall be a right/left in,
left out, and right out driveway. This 3 lane section shall extend a minimum
of 200’ or the 95% queue length, whichever is greater.
7) To the owner’s agreement to abide by the following:
a. The developer’s Professional Engineer shall demonstrate to the City by
engineering analysis submitted with the LDP application, that the discharge rate
and velocity of the storm water runoff resulting from the development is restricted
to seventy-five percent (75%) of the pre-development conditions. Locations shall
be as approved by the Stormwater Engineer.
b. The water quality and detention facilities shall utilize earthen embankments, where
possible. Walled structures are not encouraged. If walled structures are proposed,
they must meet the acceptable design standards of the Department of
Community Development.
i. Detention facility shall have a six foot high, five-board equestrian style
fence with two inch by four inch welded wire constructed around it.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
42
c. The Developer shall utilize GASWCC limited application controls. All water quality
and detention facilities shall have vegetated surfaces to be regularly maintained
by the owner.
d. Provide a maximum 75 percent impervious, per drainage basin, at maximum
build-out.
e. Provide for maximum slopes of 3:1 and a maximum disturbed area of sixteen acres
open at any time as shown on the LDP phasing plan, as approved by the
Stormwater Engineer.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
43
APPENDIX A
Comments on Public Services and Utilities
Note: Various City and/or County departments that may or may not be affected by the proposed
development provide the following information. Comments herein are based on the applicant’s
conceptual site plan and are intended as general non-binding information and in no manner suggest a
final finding by the commenter. All projects, if approved are required to complete the City of Milton Plan
Review process prior to the commencement of any construction activity.
Transportation:
• Site plan does not show all proposed improvements to site entrances including turn lanes
• Analysis indicated drive on site plan does not meet spacing minimums
• Show trip generation rates used for each land use in table
• Drive location should be shifted to the north as recommended in the study to meet minimum
spacing requirements.
• Current GDOT practice on Traffic Signal Warrants is to exclude right turning volume when a
separate right turn lane exists. At both intersections that signals are recommended, the significant
majority of the volume is right turning. With the right turn volume, these intersections would likely
meet signal warrants, but without the right turn volumes, it is likely that they would not meet
warrants. A full warrant analysis should be done on these two intersections.
• Site plan does not clearly indicate building uses.
• Underground detention is shown. Why are the lakes not used?
• Water quality features should be placed to protect the lake.
• What is the wetland study area?
• Septic system area on north property line does not seem like an appropriate area.
• Show correct buffers on both lakes and on stream.
• Clearly denote flood zones AE and X.
• Provide bus route or drop off route.
• Site plan does not show current conditions on the existing site south of this project including the
right turn lane and sidewalk.
• Delineate between vehicular and pedestrian paths on plan.
• Is there a bridge/culvert over the wetland area? No
Fulton County Health Department:
• This department recommends that the applicant be required to connect the proposed
development to public water available to the site.
• Due to the inaccessibility of public sewer to serve the proposed development, this department
recommends that individual onsite sewage management systems be utilized. However, the
“Design Limits for conventional or chamber Septic Tank Systems” for County Health Department as
defined by Georgia Department of Natural Resource (DNR) are limited by size and subsurface
introduction of effluents. Onsite sewage management systems having a septic tank capacity of
greater than ten thousand (10,000) gallons, or where the total length of absorption trenches
required, would exceed three thousand (3000) linear feet, or where the total absorption trench
bottom area required, would exceed nine thousand (9000) square feet, will be governed and
placed under the statutory authority and jurisdiction of the Department of Natural Resources.
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
44
• Due to the inaccessibility of public sanitary sewer to sewer the proposed development, this
department recommends that individual onsite sewage management systems be utilized.
However, this department will require all necessary percolation and soil data, required layouts,
and supportive data be submitted for review and determined acceptable prior to preliminary
plat and/or Land Disturbance Permit (LDP) approval.
• Since this proposed development constitutes a premise where people work, live, or congregate,
onsite sanitary facilities will be mandatory, prior to use or occupancy.
• Since this development utilizes an onsite sewage management system, the owner must obtain
approval from this department prior to issuance of a building permit and before building
construction or renovation.
• This facility must comply with the Fulton County Clean Indoor Air Ordinance.
• If this proposed development includes a food service facility, the owner must submit kitchen plans
for review and approval by this department before issuance of a building permit and beginning
construction. The owner must obtain a food service permit prior to opening.
• This department is requiring that all existing structures to be demolished must be inspected by a
certified pest control operator to insure that the premise is rat free. If evidence of rodent
infestation is found, the property must be baited prior to demotion.
• If this proposed development includes an existing individual onsite sewage management
system(s), and the system(s) will be abandoned, it shall be abandoned in accordance with Fulton
County regulations.
• If this proposed development includes an existing individual onsite water supply system(s), and the
system(s) will be abandoned, it shall be abandoned in accordance with Fulton County
regulations.
Fulton County Tax Assessor:
Property Tax ID#: 22 -4770-0909-030-3
City of Milton Fire Marshal:
Comments:
• For the Hopewell private school-Possible increase in call volume for emergency services, water
consumption demands will increase, traffic increase could slow response times, and access to the
proposed building needs to be around the entire building and to allow parking between the
building and right of way could pose a problem for emergency access.
Public Safety
• The public safety impact would be primarily traffic related, specifically during drop-off and pick-
up times in the morning and afternoon. The projected enrollment of 325 students means up to 325
additional cars on Hopewell between 7:00 and 9:00 in the morning and 2:00 and 4:00 in the
afternoon which may increase traffic congestion in the area. The school must have some means
City of Milton
Deerfield Professional Centre 13000 Deerfield Parkway Building 100, Suite 107 C Milton, GA 30004
**Meeting Codes: CZIM-Community Zoning Information Meeting; DRB-Design Review Board;
PC-Planning Commission; MCC-Mayor and City Council
W:\Board of Commissions\Planning Commission\Master PC Agenda 2.26.08\PCAGENDA FEB 26.doc
45
of managing parent-student traffic that does not result in traffic backing up and potentially
blocking Hopewell Rd during these time periods. As a two lane road, the daily influx of these
vehicles can adversely impact traffic in the area if the school has not developed a means of
keeping the road clear of waiting parents before and after school. Potential traffic hazards
include increased accidents, and restricted emergency vehicle access during these times due to
the nature of the roads and traffic patterns on Hopewell Rd. Otherwise, the impact on public
safety will be negligible.